Wales' AI zone has a neighbour problem

And Microsoft drops Essex project.

Share
Wales' AI zone has a neighbour problem
Countryside earmarked for a data centre near Pontylcun in Mid Glamorgan. Credit: Kay Page

Good morning, and happy international G&T day to all who celebrate.

It's three weeks since our scoop that Britain's flagship data centre would have to wait until the 2030s to get enough power and yesterday The Telegraph and FT reported that Microsoft had pulled out as anchor tenant of the scheme. It is a huge blow to Nscale, the neo-cloud company behind the Essex project, ahead of a planned IPO, with investors also getting cold feet last week about cloud providers' debts.

In a similar vein, today's main story comes from South Wales where almost a year ago the government announced an AI Growth Zone. Since then at least two new large data centres have been proposed, but both are about as popular in the region as an England rugby shirt. Reporter Kay Page has been speaking to locals to find out why.

It all points to a paradox I wrote about at the start of August — we've imported US levels of anxiety about data centres, despite not being able to build the things.